RCG Centre, Mitchell Street

VALUE:  
Original Price $2,479,000
Final Price $2,620,481
DESCRIPTION:
To extend the front of an existing 8 storey office building (all floors) 7 m forward to the boundary and construct a 4 storey carpark, (2 storeys underground) and underpinning the neighbouring buildings.

ROLE

Builder
PERIOD OF ENGAGEMENT:
Start Date 13 August 2000
Original Completion Date 15 March 2001
Extended Completion Date: 14 May 2002
Final Completion Date: 11 May 2001
REMARKS:  

This project was the most difficult building job seen in Darwin. It required a 7m extension to the front of the existing building, which completely took up the remaining land space, therefore had no layout area for material. It fronted busy CBD Mitchell Street making access difficult.

The project required a 2 storey deep excavation at the rear of the building for a 4 storey carpark. The only access was a single lane beside the existing building which went under the new extension at the front making timing critical. This also required underpinning to the 8 storey and 6 storey neighbouring building.

To top this off, the existing building was still occupied by tenants which restricted noise and operation time while maintaining 24 hour access to the tenant.

INNOVATION:  
Our management of the project allowed us to successfully complete the building in a professional way even with a very difficult client and a biased Superintendent.

PERSONNEL:

 
Construction Manager Jim Eadie
Site Supervisor Rob Thompson
Site Supervisor Jim Kent




 

 

 

Home - About Sunbuild - Projects Portfolio - Careers at Sunbuild - Our Awards - Contact Sunbuild

©2006 Sunbuild Pty. Ltd. This Website is protected by International Law.
Website design, search engine placement & internet advertising by Australian Business Productions