KORMILDA COLLEGE ACADEMIC BLOCK STAGE 3 - BERRIMAH

VALUE:  
Original Price $1,396,685
Final Price $1,446,932
DESCRIPTION:
Construction of an academic classroom block built of masonry construction and steel framed roof. It contained 14 airconditioned classrooms, 2 toilet blocks and stores.

 

CLIENT

Kormilda College

ROLE

Building Contractor
PERIOD OF ENGAGEMENT:
Start Date 8 July 1996
Original Completion Date 24 December 1996
Final Completion Date: 10 January 1997
Approved Completion Date: 24 January 1997
REMARKS:  
This project was of a relatively simple design but half of it had to be built over a cliff face creating difficulties in the footings area. This project was done on a bill of quantities, which had a number of provision quantities causing the price increase along with some small variations.
INNOVATIONS:  
The project was of a basic design, which did not lend itself to many alternatives, but we suggested improvements to the performance of the building. These included the installation of waterproofing to the walls of the semi-recessed ground store. This is part of our normal partnering approach to projects.

PERSONNEL:

 
Construction Manager Jim Eadie
Site Supervisor Roger Halliwell





 

 

 

 

Home - About Sunbuild - Projects Portfolio - Careers at Sunbuild - Our Awards - Contact Sunbuild

©2006 Sunbuild Pty. Ltd. This Website is protected by International Law.
Website design, search engine placement & internet advertising by Australian Business Productions