Garden of Remembrance

VALUE:  
Original Price $285,390
Final Price $327,114

DESCRIPTION:
To construct a shelter/carpark/memorial work incorporating gardens and a water feature.

CLIENT

Department of Defence

ROLE

Builder
PERIOD OF ENGAGEMENT:
Start Date 3 August 2001
Original Completion Date 25 October 2001
Final Completion Date: 9 November 2001
Approved Completion Date: 9 November 2001
REMARKS:  
This project touched the hearts of all who worked on it because of the importance of remembering those lost in the service of our country. This inspired the tradesmen to produce quality work of the highest standard. This is evident by the attention to detail in every way from the placing of the river stones to the regimental layout of the planting. This was a very memorable project for Sunbuild.
INNOVATION:  
The feature watercourse required very close liaison with the Consultants to achieve the performance and aesthetic effect required. We hand selected the stone pitching in the water course and carefully placed each stone in the concrete while it was setting. The Consultants worked with us on each of the pours to ensure the required effect was achieved.

PERSONNEL:

 
Construction Manager Jim Eadie
Site Supervisor Rob Thompson







 

Home - About Sunbuild - Projects Portfolio - Careers at Sunbuild - Our Awards - Contact Sunbuild

©2006 Sunbuild Pty. Ltd. This Website is protected by International Law.
Website design, search engine placement & internet advertising by Australian Business Productions