Tindal RAAF Base –
ACS Facility Upgrade

VALUE:  
Original Price $1,263,189
Final Price $1,329,450

DESCRIPTION:
A single storey steel structure clad with custom orb. All the external envelope has been designed to accommodate the external noise transmission from aircraft. Effectively this building houses offices, meeting and training rooms.

CLIENT

Department of Defence

ROLE

Design and Construct

Subconsultants

- TCM Pty Ltd
- MKEA
PERIOD OF ENGAGEMENT:
Start Date 8 March 2001
Original Completion Date 8 July 2001
Final Completion Date: 25 July 2001
REMARKS:  
This Project ran extremely smoothly. Whilst final completion was achieved on 25th July 2001, the project was completed 4 weeks earlier. The project couldn’t be handed over until the loose furniture arrived and was installed through a nominated supplier.
INNOVATION:  
The mechanical brief required a system to be designed with minimal capital cost and on-going energy efficiency. This was achieved by installing a 3 stage APAC unit and through a sophisticated DDC programme. Splitting up the building into 5 zones allowed the minimum use of power as each zone came on line only as required.

PERSONNEL:

 
Project Designer Neil Sunners
Construction Manager Jim Eadie
Site Supervisor Stephen Lees


 

Home - About Sunbuild - Projects Portfolio - Careers at Sunbuild - Our Awards - Contact Sunbuild

©2006 Sunbuild Pty. Ltd. This Website is protected by International Law.
Website design, search engine placement & internet advertising by Australian Business Productions